Anderson Road works next week- Power Station to Middle Beach Road
Works will commence next week on the reconstruction and sealing of Anderson Road between the Powerhouse and Middle Beach Road. The road will be closed to vehicles, bikes, and pedestrians during certain stages of works.
Work will start on Tuesday 17 September and continue for an estimated six weeks. Weather may affect these timeframes. Full road closure may be in effect for several days at a time. A householder will be released next week with approximate timeframes of the full closure.
Every effort will be made to allow half-road closures so businesses, residents, and emergency services have access to residences along this section of road. Residents and businesses will be contacted in the coming days to discuss movements.
To ensure the safety of workers and the community, please obey road signs and directions from road works staff. Thank you for your cooperation.
Please direct any enquiries to Brad Josephs, Manager Infrastructure and Engineering Services on 6563 2066 or [email protected].